1, to participate in the construction of the relevant personnel must be admitted before the safety education, the examination before the induction.
2, to enter the scene of the construction gantry crane operators must be in accordance with the provisions of clothing, and wear good safety protection supplies.
3, Special operations personnel must hold a certificate, not special operations personnel.
4, before the commencement of the responsible person should organize construction, technical security personnel on-site inspection, in line with the requirements can start.
5, before the construction work should do a good job of safety technology disclosure, and according to the requirements of the record.
6, the site construction personnel should strictly abide by the safety regulations and related safety management provisions, the correct use of equipment, subject to the management of security personnel.Gantry Crane
7, the construction personnel must fasten the safety belt in the high place, the seat belt fixed position should be safe and reliable, and as far as possible high hanging low use.
8, Ladder, platform, channel, etc. must be solid and reliable, pro-air, suspended work must hang good safety nets.
9, single girder crane construction equipment, tools, etc. should be regularly inspected, maintained and maintained.
10, lifting, transportation equipment operators before the operation of the safety of equipment to check, to ensure safe operation of equipment.
11, transshipment and lifting operations should be carried out before lifting or bundling appliances and facilities for inspection, correct selection and use, and strictly implement the "Ten not hanging" provisions to ensure that their safety meets the requirements.Gantry Crane
12, large lifting must be strictly carried out lifting plan, unified command, coordination.
13. When the component is docked, it is forbidden to find the right hand hole.
14, electrical system power commissioning, must have two people at the same time operation, one of the guardianship.
15, the lifting crane operation should be set to command and wear the armband, and command clear, the signal clearly unified, the personnel involved in the construction must obey the management, unified action.Gantry Crane
16, the installation site should be set up security operation Cordon, and send a security guard personnel, prohibit unrelated personnel into.
17, the construction site should be hoisted the necessary safety signs.
18, security personnel should adhere to the site inspection, found that violations must be promptly stopped and dealt with.
19, installation operations, when there are six or more gales and thunder, rain, snow, fog should stop operation.Gantry Crane